CR106 Design & Construction of Loyang Station

Project Description

Bachy Soletanche Singapore’s scope of work for Contract CR106 involves foundation and earth retaining works in relation to the design, construction, and completion of Loyang Station and associated structures. The project includes cut-and-cover (C&C) tunnels, bored tunnels connecting Loyang Station to Pasir Ris East Station, a Tunnel Boring Machine (TBM) receiving shaft, and an elevated infrastructure. The works are carried out under mixed ground conditions comprising Fill, Old Alluvium, and Bukit Timah Granite.

Project Information 

Diaphragm Wall: 278m; 1,200mm thickness; 13,304m3 excavation; 12,390m3 concrete; 40m average depth

 

Owner:

Land Transport Authority (LTA)

Engineer:

Meinhardt Infrastructure Pte Ltd

General Contractor:

Woh Hup (Private) Limited – Dongah Geological Engineering Co., Ltd, Singapore Branch Joint Venture

Year:

2024