Project Description

We Build the Foundation of Smart Cities

DSTA LCK Shaft

Project Description

Diaphragm Wall Works for the Lifting Shaft for Construction of Drains, Sewers, Water Pipelines and Ancillary Works at Lim Chu Kang.
The scope of works for Bachy Soletanche Singapore comprises the construction of ten (10) Diaphragm-wall panels forming a 20m internal diameter lifting shaft, as part of the construction of drains, sewers, water pipelines and associated ancillary works at Lim Chu Kang.

Project Information 

Diaphragm wall : Approximately 67m length, comprising 1200mm thick D-wall extending to a depth of 39m.

Excavation: 3,134m3

Concrete: 3,037m3

Owner:

DSTA – Defence Science and Technology Agency

Design Engineer:

AECOM

Main Contractor:

KTC Civil Engineering & Construction Pte Ltd

Year:

2022